Sampling & Mold Development

Free stock samples, USD 100–200 custom samples at 7–10 days, what an approval must cover, and the 35–42 days a new mould takes.

Two kinds of sample, one approval that actually means something, and the 35–42 days a new mould costs before any production can start. If you are planning a launch date, this is the page that tells you whether it is achievable.

At a glance

  • Stock sampleFree — you pay courier, or give a DHL / FedEx / UPS account
  • Custom sampleUSD 100–200, depending on product and decoration
  • Sample lead timeAbout 7–10 days
  • New mould35–42 days, depending on structure and complexity
  • Production25–35 days after specifications are confirmed
  • ReferenceThe approved sample is the QC standard

Two kinds of sample, two different jobs

Stock sample Custom sample
What you get An existing mould, stock colour, no decoration Your colour, your printing, your finish on the real substrate
What it answers Shape, capacity, wall feel, mechanism — is this the right starting point? Will the brand actually look like this on the shelf?
Cost Free; freight only USD 100–200
Time Dispatch as soon as stock allows About 7–10 days

What an approval should actually cover

  1. Colour against the chip, in daylight — not against the photo you sent, and not under an office lamp.
  2. Fit — cap to body, plug to orifice, actuator to stem, insert to jar. Fit is a dimension, not an opinion.
  3. Decoration position — the logo relative to the seam, the front face, the opening direction. Judge it with the artwork in hand.
  4. Function — torque, leakage, actuation, crush on the tube shoulder. Test it the way your filling line will.
  5. Packing — divider, bag, carton count. This is the step people skip, and it is where transit damage comes from.

Opening a new mould

  1. Brief and DFMStructure, capacity, wall thickness and decoration are agreed against the tooling, before steel is cut.
  2. ToolingMould built to the agreed drawing. Changes at this stage are cheap; changes after T1 are not.
  3. T1 samplesFirst parts off the tool, measured and compared with the drawing.
  4. Report and correctionDimensions, fit and appearance reviewed; the tool is adjusted where it falls outside.
  5. T2 and approvalRevised parts, then the signed sample that becomes the production reference.

Working backwards from a launch date

Typical factory time, using the figures above: 35–42 days for a new mould, 7–10 days for the sample after that, 25–35 days for production after approval — roughly three months before freight. Add transit and import clearance on top.

That is a planning figure, not a promise: quantity, decoration stages and the factory’s schedule move it. But it explains why a launch in June needs a mould decision in February, and why a stock-mould project with the same date has two months of slack the custom one does not.

What it costs to change a decision later

  • Structure after T1 — tool rework and a second sample cycle.
  • Colour after spraying — re-matching, and a batch that will not match the first one exactly.
  • Decoration after plating — new screens or plates, plus a re-run of the print stage.
  • Quantity after material is ordered — re-quoting, and a carton plan that no longer fits the container.
A sample you have not tested is a sample you have not approved. Fill it, cap it, drop it in its carton, leave it in a warm room for a week. Problems found at this stage cost a week; the same problems found after 10,000 units cost a container.

Ask for a stock sample in the sampling question, or start a project and tell us the product and the date you need it.

Start a Project

Start a project

Send the artwork, the quantity and the date you need it.

You get a written quotation, a sample plan and a production schedule — with the tolerances and the minimum order stated instead of left to discover later.